I have designed an application to keep track of employees' weekly projects. Basically they want to enter the hours they worked for each project throughout the week.

  1. In the first screenshot, users choose the week, enter their name, create a project in the left box. Once they hit "Add", a row will be added to the grid on the right. Then users can enter the hours for each day.

  2. They can continue until they finish adding all the projects. The result is the second screenshot.

The biggest concern is that initially all the information was displayed in the grid. Should I separate the project from its hours (as shown here)? Or should I keep them in the same grid even each row will be much wider?

enter image description here

enter image description here

share|improve this question
    
Design critiques are off topic. If you have a specific question about a specific part of the user experience then ask that instead. –  ChrisF Sep 24 '12 at 13:14
    
I see. I'll rephrase the question. Thank. –  wcdomy Sep 24 '12 at 13:15
    
The question has been closed until you can reword it as per ChrisF's suggestion. You can edit using the 'edit' option below the question and then use the 'flag' option to alert the moderators that you've updated it. Providing the question meets the requirements of questions here we'll be able to reopen it for you. –  JonW Sep 24 '12 at 13:33
add comment

1 Answer 1

up vote 2 down vote accepted

You should separate project entry and time entry into separate screens. Why? Because nine times out of ten, the employee will use the tool to track time for a pre-existing project. So from a user-centered design point of view, you should design the main screen to support the main use case.

How we do it where I work is that project leads manage projects and regular employees just do time tracking. This makes sense from the perspective that project leads know the facts and details about projects (like how much we charge per hour, and how billable it is), but also because project leads' job includes boring stuff like making projects in a time tracking tool. Regular employees should be shielded from non-essential stuff as much as possible, so we make sure they don't have to do much else than jump into the tool, enter their hours, and then close the app once a day.

share|improve this answer
    
Good point Rahul. That's exactly what I'm thinking. Thank! –  wcdomy Sep 24 '12 at 14:37
add comment

Your Answer

 
discard

By posting your answer, you agree to the privacy policy and terms of service.

Not the answer you're looking for? Browse other questions tagged or ask your own question.